01
Convert the site load from kW to kVA
Generators are commonly rated in kVA while electrical equipment may be listed in kW. For a simple balanced load, kVA equals kW divided by power factor. A 100 kW load at 0.8 power factor is therefore 125 kVA before starting currents, load steps or engineering margin are considered.
02
Allow for motors and starting current
Motors, pumps, compressors and refrigeration equipment can draw several times their running current while starting. Direct-on-line starts usually create a larger demand than star-delta, soft-start or variable-speed arrangements. The largest starting event and sequence should be checked against generator voltage-dip performance.
- List each load in kW, kVA or amps
- Identify single-phase and three-phase equipment
- Record the largest motor and its starting method
- Separate essential loads from loads that can remain off
- Confirm whether the duty is standby or prime
03
Include site and future requirements
Altitude, ambient temperature, non-linear loads, uneven phase loading and planned expansion can affect the final selection. Avoid adding an arbitrary percentage without understanding the load: too small risks unstable power, while excessive oversizing can increase cost and lead to poor diesel-engine loading.